206 km of transmission and distribution lines. The diameter
size of these pipelines varied from 80 mm to 500 mm. The
pipe material was ductile iron.
|
| |
Supply and installation of various types of hydraulic
accessories such as: single air valve, double air valve,
pressure reducing valve, float valve...
|
| |
Construction of five new elevated water towers of 36
m height and a capacity of 100 and 250 meter cube.
|
| |
Rehabilitation of 5 existing water towers of 20 m height
and a capacity of 85 meter cube.
|
| |
Construction of one rectangular reservoir, capacity
2500 meter cube.
|
| |
Construction of 30 new circular reservoirs, capacity
from 50 meter cube to 250 meter cube.
|
| |
Rehabilitation of 50 existing reservoirs, capacity from
25 meter cube to 500 meter cube.
|
| |
Drilling and installing electro-mechanical equipment
(pumps, chlorination) for five new boreholes, diameter
of 14 , depth
of 450 m.
|
| |
Construction and installation of electro-mechanical
equipment for two new pumping stations containing three
booster pumps capacity 20 l/s.
|

|
PROJECT PARTICULARS:
Average monthly pipeline production 12 km.
Peak monthly pipeline production 16 km.
Hydraulic design and shop drawings.
Duration: 24 months, Bulk of work executed in 16 months.
Joint venture agreement with CFE of Belgium.
FIDIC contract conditions (Main contract). |